একটা বিল্ডিং এর সকল আইটেম মিলে ১০০% কিভাবে ভাগ করা হয়!

একটা বিল্ডিং এর সকল আইটেম মিলে ১০০% কিভাবে ভাগ করা হয়।

উত্তর:-

1. Structure = 35%

2. Brick work = 6%

3. Wood work = 5%

4. Metal work = 2%

5. Plambing and Sanitary = 6%

6. Electrical work = 7%

7. Plaster work = 4%

8. General Floor Tiles work = 6%

9. Toilet & Kit wall Tiles work = 3%

10. Aluminium work = 4%

11. EME (Lift, Generator, Substation) = 10%

12. Paint work = 3%

13. Others civil work = 6%

14. Utility connection & Bill = 3%

Total = 100%

STRUCTURE 35%

– Footing & Column Padestal = 20%

– Grade Beam, UGWR top Slab = 5%

– GF Column, Stair etc = 4%

– 1st Floor Slab = 9%

– Typical Floor Column (5×3%) = 15%

– 2nd floor slab to roof slab (5×8) = 40%

– Roof top = 7%

TOTAL = 100% (৩৫% যেভাবে আসবে।)

BRICK WORK 6%

– GF Brick work = 6%

– 1st floor Brick work = 18%

– 2nd floor Brick work = 18%

– 3rd floor Brick work = 18%

– 4th floor Brick work = 18%

– 5th floor Brick work = 18%

-Roof Top Brick work = 4%

TOTAL = 100% (৬% যেভাবে হবে।)

WOOD WORK 5%

– Door frame = 40%

– Main Door Shutter = 15%

– Partex Door Shutter = 35%

– Cat Door & Accessories = 10%

TOTAL = 100% (৫% যেভাবে হবে।)

METAL WORK 2%

– Window grill = 55%

– Verandah Railling = 20%

– Stair Railling = 10%

– Main gate, Gen-Sub, safety grill = 15%

TOTAL = 100% (২% যেভাবে হবে।)

PLAMBING & SANITARY 6%

– uPVC vertical line thru duct = 25%

– GI line work = 30%

– Fixture & Fittings = 40%

– Ground Floor = 5%

TOTAL = 100% (৬% যেভাবে হবে।)

ELECTRICAL – 7%

– Conduiting inside slab = 10%

– Conduiting on wall i/c MK box=15%

– Cabling work = 55%

– Switch-Socket = 20%

TOTAL = 100% (৭% যেভাবে হবে।)

PLASTER 4%

– Ceiling plaster = 20%

– Internal wall plaster = 50%

– Outside plaster/facing bricks = 30%

TOTAL = 100% (৪% যেভাবে হবে।)

GENERAL FLOOR TILES 6%

– General floor & Verandah = 75%

– Stair, typical lobby & lift wall = 20%

– GF lift lobby, wall, reception = 5%

TOTAL = 100% (৬% যেভাবে হবে।)

TOILET & KIT WALL TILES = 3%

– Bath wall = 60%

– Kitchen wall = 20%

– Bath floor = 9%

– Bath counter top = 4%

– Kitchen floor = 3%

– Kitchen counter top =4%

TOTAL = 100% (৩% যেভাবে হবে।)

ALUMINIUM WORK 4%

– Outer framing-window sliding= 40%

– Glass shutter-window sliding = 30%

– Verandah sliding = 20%

– Toilet high window = 5%

– Comnon area = 5%

TOTAL = 100% (৪% যেভাবে হবে।)

EME 10%

– Lift = 50%

– Generator = 25%

– Substation = 20%

– PABX, Fire extinguisher etc = 5%

TOTAL = 100% (১০% যেভাবে হবে।)

PAINT WORK = 3%

– Upto putty = 40%

– Internal wall&ceiling 1st coat= 20%

– Internal wall&ceiling 2nd coat= 15%

– Outside paint/ceramic Tites = 25%

TOTAL = 100% (৩% যেভাবে হবে।)

OTHERS CIVIL WORK = 6%

– Boundary wall = 30%

– Line terracing/Roof top paver= 15%

– LOGO, Gardening & others = 4%

– GF BBC = 14%

– GF pavement & footpath dev = 10%

– Lintel, F/slab, drop wall, counter slab = 20%

– Cable tray = 1%

– Sanitary duct cover, ceiling etc= 4%

– Reception desk, letter box = 2%

TOTAL = 100% (৬% যেভাবে হবে।)

UTILITY CONNECTION & BILL = 3%

– DESA/DESCO = 35%

– TITAS = 20

– WASA = 15%

– Utility bills = 30%

TOTAL = 100% (৩% যেভাবে হবে।)